Permits Index
10
Permits, 24 months
20 on record
16
Roofing permits
Jul 8, 2026
Last permit issued
17
Addresses with a page

Roofing: 16 permits

From Jul 20, 2020 to Jul 8, 2026. Across 7 roofing permits since October 3, 2024, most declared values run from $2,800 to $6,080 (the middle 80%); the median is $3,600 and half fall between $3,050 and $4,500. The lowest on record is $2,800 and the highest $8,000.

Since October 3, 2024, 7 listed below. Earlier permits, 9, are on their house pages: 2024: 1 · 2023: 5 · 2022: 1 · 2021: 1 · 2020: 1.

IssuedWorkBuildingDeclared valueContractor as filedPermit
Jul 8, 2026Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing 24 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BDwelling - Single Family$4,800—26016-90000-17956
Feb 3, 2026Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing 14 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BDwelling - Single Family$2,800—26016-90000-03194
Nov 21, 2025Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing 14 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BDwelling - Single Family$2,800—25016-90000-34492
Sep 29, 2025Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing 21 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BDwelling - Single Family$4,200—25016-90000-29184
Jun 2, 2025Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over new solid sheathing Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roofing Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BDwelling - Single Family$8,000—25016-20000-17769
Jan 10, 2025Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing 18 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BDwelling - Single Family$3,600—25016-90000-00757
Oct 21, 2024Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over new solid sheathing 11 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BDwelling - Single Family$3,300—24016-90000-33691

Heating and cooling: 4 permits

From Nov 7, 2023 to May 23, 2025. Fewer than 5 heating and cooling permits since October 3, 2024 carry a declared value, so no range is computed; the rows are below.

Since October 3, 2024, 3 listed below. Earlier permits, 1, are on their house pages: 2023: 1.

IssuedWorkBuildingDeclared valueContractor as filedPermit
May 23, 2025Bldg-Alter/Repair: ENCLOSE FRONT PORCH AND REAR PATIO COVER TO HABITABLE SPACE AND REMODEL TO SFD, KITCHEN AND BATHROOM REMODEL, ADDITION OF NEW DECK AND WINDOW CHANGE OUT AND ROOF FRAMING WORK. ALL WORK PER EOR. SEE COMMENTS "COMPLY WITH DEPARTMENT ORDER effective date10/31/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"Dwelling - Single Family$45,000—25016-10000-03431
Jan 6, 2025Bldg-Alter/Repair: 11 window . Window and door change-out (same size & type) for residential buildings. Dual glazing, labeled and certified by National Fenestration Rating Council , is required for doors and windows replaced in all residential buildings, three stories or less, per Title 24, Part 6, Section 150.2 1BDwelling - Single Family$2,750—25016-90000-00296
Oct 21, 2024Bldg-Alter/Repair: 3 window . Window and door change-out (same size & type) for residential buildings. Dual glazing, labeled and certified by National Fenestration Rating Council , is required for doors and windows replaced in all residential buildings, three stories or less, per Title 24, Part 6, Section 150.2 1B.1 bathroom .Bathroom remodel for residential buildings .6 door . Window and door change-out (same size & type) for residential buildings. Dual glazing, labeled and certified by National Fenestration Rating Council , is required for doors and windows replaced in all residential buildings, three stories or less, per Title 24, Part 6, Section 150.2 1B.Kitchen remodel for residential buildingsDwelling - Single Family$14,400—24016-90000-33690

Addresses on this street with a page

Source

Los Angeles Department of Building and Safety, via the city open-data portal, pulled nightly. As of October 3, 2026. Storm dates touching this street will appear here once the hail record is attached.