13
Permits, 24 months
52 on record
29
Roofing permits
Aug 18, 2026
Last permit issued
43
Addresses with a page

Roofing: 29 permits

From Oct 16, 2020 to Aug 18, 2026. Across 9 roofing permits since October 5, 2024, most declared values run from $7,400 to $448,000 (the middle 80%); the median is $35,000 and half fall between $13,500 and $240,000. The lowest on record is $5,000 and the highest $500,000.

Since October 5, 2024, 9 listed below. Earlier permits, 20, are on their house pages: 2024: 1 · 2023: 7 · 2022: 5 · 2021: 5 · 2020: 2.

IssuedWorkBuildingDeclared valueContractor as filedPermit
Aug 18, 2026Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing _380_Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BApartment$240,000—26016-20000-21842
Jan 7, 2026Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing 490 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BCommercial$98,000—26016-90000-00512
Sep 22, 2025Bldg-Alter/Repair: TENANT IMPROVEMENT TO EXISTING RETAIL FOOD STORE INCLUDING NEW REFRIGERATION FROM GAS TO CO2 ON THE ROOF AND FREEZER CASES <NEW AWNING UNDER SEPARATE PERMIT>Retail$500,000—25016-10000-08669
Sep 12, 2025Bldg-Alter/Repair: Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over existing solid sheathing __30____Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement>50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part6, Section 141 2BApartment$13,500—25016-30000-27603
Jul 31, 2025Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roofing Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BRetail$15,000—25016-20000-23420
Jul 22, 2025Bldg-Alter/Repair: Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over existing solid sheathing _ _Squares. Class A roof covering is required within a Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BDwelling - Single Family$8,000—25016-30000-22481
Apr 8, 2025Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing 25 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BApartment$5,000—25016-90000-10762
Mar 27, 2025Bldg-Alter/Repair: Repair Fire Damaged Existing Building. <Supplemental permit is required for the roof trusses as deferred submittal.>Office$435,000—23016-10000-43934
Nov 6, 2024Bldg-Alter/Repair: Supplemental to permit 23016-10000-43934 for Roof Barrel Truss Replacement for Fire Damaged BuildingRetail$35,000—23016-10001-43934

Plumbing: 9 permits

From Jan 7, 2020 to Feb 26, 2026. Fewer than 5 plumbing permits since October 5, 2024 carry a declared value, so no range is computed; the rows are below.

Since October 5, 2024, 3 listed below. Earlier permits, 6, are on their house pages: 2023: 1 · 2022: 2 · 2021: 1 · 2020: 2.

IssuedWorkBuildingDeclared valueContractor as filedPermit
Feb 26, 2026Bldg-Demolition: Permit 2 of 2 Demolition of Storage Building 40'x60' (Per permit # 1948LA33829)Sewer Cap not requiredStorage Building$2,000—25019-10000-02271
Feb 20, 2026Bldg-Demolition: DEMO OF EXISTING PARKING LOT OFFICE BUILDING. SEWER CAP REQUIREDDemolition$4,590—25019-10000-01776
Feb 17, 2026Bldg-Demolition: Eplan:Permit 1 of 2Demolition of existing Spray Paint Booth 25'x40' (Per permit # 1945LA09706).Sewer cap required. Permit 2 of 2 Under 25019-10000-02271Demolition$501—25019-10000-02140

Heating and cooling: 9 permits

From Jan 8, 2020 to Jul 1, 2025. Fewer than 5 heating and cooling permits since October 5, 2024 carry a declared value, so no range is computed; the rows are below.

Since October 5, 2024, 1 listed below. Earlier permits, 8, are on their house pages: 2024: 1 · 2023: 2 · 2022: 1 · 2021: 2 · 2020: 2.

IssuedWorkBuildingDeclared valueContractor as filedPermit
Jul 1, 2025Bldg-Alter/Repair: Window change-out (same size & type) for residential buildings. Dual glazing, labeled and certified by National Fenestration Rating Council , is required for doors and windows replaced in all residential buildings, three stories or less, per Section 150.2 1B of Title 24Apartment$1,500—25016-10000-18058

Solar: 4 permits

From Feb 11, 2020 to Jan 26, 2024. Fewer than 5 solar permits since October 5, 2024 carry a declared value, so no range is computed; the rows are below.

Since October 5, 2024, 0 listed below. Earlier permits, 4, are on their house pages: 2024: 1 · 2022: 1 · 2021: 1 · 2020: 1.

IssuedWorkBuildingDeclared valueContractor as filedPermit

Electrical: 1 permit

From Jul 9, 2021 to Jul 9, 2021. Fewer than 5 electrical permits since October 5, 2024 carry a declared value, so no range is computed; the rows are below.

Since October 5, 2024, 0 listed below. Earlier permits, 1, are on their house pages: 2021: 1.

IssuedWorkBuildingDeclared valueContractor as filedPermit

Addresses on this street with a page

Source

Los Angeles Department of Building and Safety, via the city open-data portal, pulled nightly. As of October 5, 2026. Storm dates touching this street will appear here once the hail record is attached.