IssuedWorkTradeDeclared valueContractor as filedStatusPermit
Jan 28, 2026otc alterations permit: 11th floor: suite #1100:shell consists of selective interior demo including non-structural partitions. new construction includes interior nonstructural partitions, doors finishes, lighting, electrical, restroom upgrade, a movable partition with structural calculations. mep, fire, sprinklerElectrical$1,291,490—issued202512222376
Oct 29, 2025otc alterations permit: 12th fl suite 1200: selective interior demolition of non structural elements that include interior partitions, doors, finishes, ceilings, lighting, mechanical, electrical outlets and switches. construction includes partitions, doors, finishes, lighting, millwork, mech, electrical and plumbing unit 0Plumbing$498,950—issued202510217749
May 7, 2025otc alterations permit: 10/f : selective interior demo of non-structural elements. interior partitions, doors, finishes, lighting, mechanical, & electrical outlets and switches. refer to mech and electrical plans. fls and fire sprinkler drawings will be submitted separately. scope does not affect fixture unit 0Electrical$350,000—issued202504305515
May 7, 2025otc alterations permit: 10th fl suite 1030: selective interior demo of non structural elements. interior partitions, doors, finishes, lighting, mechanical and electrical outlets & switches. refer to mech & elec plans. f/l/s and fire sprinkler drawings submitted under separate permit unit 0Electrical$691,006—issued202504305514
Mar 31, 2025otc alterations permit: 14th/f: selective demo & minor construction of interior partitions, doors, finishes, & lighting ref to mech & electrical plans. fire/life safety & sprinkler drawings will be submitted sepratedly, scope of work does not affect fixture quantities, occupany load & calculation or path of travel unit 0Electrical$650,000—issued202503273173
Feb 13, 2025otc alterations permit: ground floor- revision of 202410032227- deferred mep to retain electrical closet and associated mep unit 0Electrical$1—issued202412177016
Oct 4, 2024otc alterations permit: rev 202405152157- 8th floor- duct distruction is being modified per space plan. 2 vav boxes are being added. no fsds are being added unit 0Heating and cooling$184,208—issued202406204850
May 10, 2024otc alterations permit: path of travel set for 550 california st, documenting full accessibility compliance, including primary entrance to building, parking, ev charging spaces, and elevator accessibility unit 0Electrical$5,000—issued202404180234
Aug 24, 2023otc alterations permit: consisting only of barrier removal: provide designated accessible parking spaces for new ev charging stations. ev charger installation was previously approved under separate electrical permit# ew202306232040 unit 0Electrical$5,000—Finaled Aug 30, 2023202308214831
Jun 2, 2022otc alterations permit: comply w/nov #202286616. repairs to sub-sidewalk basement roof slab unit 0Roofing$355,000—Finaled Oct 7, 2022202202117844
Apr 7, 2021otc alterations permit: 7th flr. conversion of offices / finishes / lighting. conference rooms, huddle and focus rooms remodel. upgrade all fixtures to new led lighting. hvac upgrade for new remodel unit 0Heating and cooling$1,540,000—cancelled202012090656
Feb 4, 2021otc alterations permit: ref. p/a 2020-0915-4208. 11th floor fpa electrification: add strobe power supply; spkr/strobes; spkrs; strobes; control relays; pilot relays; control module; duct detectors; dual monitor modules; aux relays; smoke detectors; pull stations; 2-way unit 0Heating and cooling$61,300—Finaled Mar 9, 2021202012100800
Oct 23, 2020otc alterations permit: 11th flr. office remodel of new break room, change of existing furnitures in areas of work w/ new conference rooms, new focus rooms, and new finishes. new mechanical and electrical work for new spaces unit 0Electrical$137,000—Finaled Apr 22, 2021202009154208
Feb 20, 2020otc alterations permit: fire as built 201909242464 as built changes as follows update location of 1 smoke detector, 1 duct detector, 1 2 way call station, replace 2 pendant mount smoke det w 1 duct detectorHeating and cooling$1—Finaled Sep 1, 2023202002194776
Nov 12, 2019otc alterations permit: remodel of video library: audio control rm. & audio suite upgrade all light fixture in suite to new led lighting, hvac upgrade for remodel unit 0Heating and cooling$34,500—Finaled Jun 5, 2020201908027718
Oct 21, 2019additions alterations or repairs: 4th fl:fire alarm modification. add slc card,1 rps, 34 sprkn/strobes, spkr, 3 strobes, 27 duct detectors,26 dual monitor modules,46 aux relays, 2 way call station,replace with new 3 mps,10 smoke detectors, nac module, 3 monitor modules,1 control relays, demo fa devies as shown on sheet f7.41 unit 0Heating and cooling$80,000—Finaled Nov 7, 2019201909272972
Oct 8, 2019additions alterations or repairs: 3rd floor, fa modification - ref pa #2019/0405/7249 add 1 slc card, 1 rps, 32 sprinklers/strobes; 8 sprinklers, 2-way comm call box; control relays; 21 pilot relays; 9 duct detectors;16 dual monitor modules; 30 aux relays; 15 smoke detectors; demo devices per sheet f7.41 unit 0Heating and cooling$85,560—issued201909242464
May 23, 2019otc alterations permit: ref 201812177954 revision to 201901180674 coh 1 scope of work - add 2 rib relays, 1 control relay, 1 duct det, 1 smk det, 2 dual monitor modules unit 0Heating and cooling$3,900—Finaled Aug 16, 2019201905231477
Jan 18, 2019otc alterations permit: fire alarm modification 6th fl add 37 spkr strobes, 5 speakers, 9 control relays, 19 duct det, 25 rb relays, 16 dual monitor modules, 30 pam 1 relays, replace 9 smoke det, 1 nac control module, 3 pull staions, 1 monitor module ref 201901180676Heating and cooling$15,000—Finaled Jul 24, 2019201901180676
Jan 18, 2019otc alterations permit: fire alarm modification 2nd fl add 1 slc cand, 4 spker strobes, 2 spkers, 2 strobes, 10 control relays, 15 duct det, 19 rib relays, 14 monitor modules, 26 pam relays, nac module, battery cabinetSolar$49,300—Finaled Aug 16, 2019201901180674
Sep 18, 2018otc alterations permit: 9th flr - as built for 201809109503 & 201804277568 additional scope is to correct previously approved as built #2018-0910-9503 to correct the heat pump/transfer fans matrix. maher na unit 0Heating and cooling$1—Finaled Oct 1, 2018201809180570
Sep 14, 2018otc alterations permit: 5th floor:as-built-l1)5 duct detect replaced with pendant mount smoke det. 2)1 dect det. replaced with new. 3) 3 monitor modules replace with new. 4) 6 pull station replaced with new. 5)1 nac module replaced with new . 6) add 4 pam relays, 1 moniter modules & 12 control relays. ref app#201805310552Heating and cooling$5,000—Finaled Oct 9, 2018201809140201
May 23, 2018otc alterations permit: 9th fl fire alarm modification. 19 spkr strb, 8 spkrs, 16 duct det, 9 control relays, 20 rib relays, 12 dual monitor modules, 24 pam relays, 1 analog sic board, battery cabinet with batteries, replace 15 speaker strobes with new; n/a maher; ref pa t.i. 201803083147Solar$69,000—Finaled Oct 1, 2018201804277568
May 24, 2017otc alterations permit: builts for replacement of electrical riser - revision m drawings. ref #2014-1114-1483. removed 4th fl hvac from scope of work. maher na unit 0Heating and cooling$1—Finaled Jul 13, 2017201705237392
Nov 14, 2016otc alterations permit: built for pa 2016-0607-9269. re-numbered heat pump id's. maher na unit 0Heating and cooling$1—Finaled Nov 15, 2016201611142540
Jun 7, 2016otc alterations permit: fire alarm system addition to 8th fl. add 7 ceiling speaker strobes, 4 ceiling speakers, 1 control relay for heat pump, 4 rib relay, 3 duct detectors at heat pump, 20 pam 1 relays. replace 18 ceiling speaker strobes, replace 3 wall strobes with combo wall speaker strobes, upgrade strobe powerHeating and cooling$20,000—Finaled Nov 14, 2016201606079269
May 25, 2016otc alterations permit: pa 2014-1114-1483. fire alarm modification to install smoke detectors, duct detector for heat pump, duct detectors for tsd and strobe. n/a for maher unit 0Heating and cooling$7,100—Finaled Jul 7, 2017201605248188
May 12, 2016otc alterations permit: 4th floor: extg server room expansion with new hvac, ups and power distribution. n/a for maherHeating and cooling$350,000—Finaled Mar 14, 2017201605046469
Jan 28, 2016additions alterations or repairs: replace existing diesel fire pump with a new electric fire pump fed from a life safety generator (like for like replacement rated 500 gpm @100 psi); maher n/a unit 0Electrical$215,000—issued201507171875
Dec 18, 2015otc alterations permit: sprinklers ti on 2 basements, flors 2,5,6,12- relocate 8 fire sprinklers. offset 21 sections of pipe under electrical conduit. ref app# 201411141483. n/a for maherElectrical$9,500—Finaled Oct 13, 2017201512185473
Jul 29, 2015additions alterations or repairs: replacement of 480v bus duct riser distribution system which includes removal of service switchboard 3 cables iwth new 480v calbe riser distriburion and switcher. maher/na unit 0Heating and cooling$3,000,000—Finaled Jul 13, 2017201411141483
Jun 26, 2015otc alterations permit: penthouse: f.a. t.i. 4 replace duct smoke detectors, 6 monitor modules, 4 mother boards, 12 relocate modules to accommodate the demo and replacement of the supply and return fans. n/a for maher. ref app#201504304990Heating and cooling$13,364—Finaled Jul 9, 2015201506260025

On California St

1,703 permits on record on California St.

TradePermitsSince Oct 6, 2024Median declaredRangeLast
Roofing30551$22,000$8,978–$198,000Jul 20, 2026
Electrical535104$100,000$3,000–$785,000Sep 23, 2026
Heating and cooling51370$33,865$1,470–$385,794Sep 21, 2026
Plumbing32760$90,392$3,450–$747,457Oct 1, 2026
Solar144—under 5May 7, 2026
Water heater93—under 5Sep 4, 2026

Roof replacement cost in San Francisco

Across 5,872 one- and two-family reroof permits since October 6, 2024, most declared values run from $7,655 to $32,000 (the middle 80%); the median is $15,000 and half fall between $10,800 and $21,792. The lowest on record is $1 and the highest $4,315,170. Every permit behind that range.

Furnace, heat pump or air conditioner replacement cost in San Francisco

Across 293 one- and two-family heating and cooling permits since October 6, 2024, most declared values run from $21 to $223,693 (the middle 80%); the median is $25,996 and half fall between $5,000 and $120,000. The lowest on record is $1 and the highest $1,600,000. Every permit behind that range.

Source