30
Permits, 24 months
83 on record
61
Roofing permits
Sep 17, 2026
Last permit issued
72
Addresses with a page

Roofing: 61 permits

From Sep 11, 2020 to Sep 17, 2026. Across 29 roofing permits since October 3, 2024, most declared values run from $3,800 to $30,900 (the middle 80%); the median is $10,000 and half fall between $5,500 and $17,000. The lowest on record is $1,400 and the highest $280,000.

Since October 3, 2024, 29 listed below. Earlier permits, 32, are on their house pages: 2024: 8 · 2023: 12 · 2022: 3 · 2021: 4 · 2020: 5.

IssuedWorkBuildingDeclared valueContractor as filedPermit
Sep 17, 2026Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing ___26__Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2B. DETACHED GARAGE INCLUDEDDwelling - Single Family$4,000—26016-10000-24991
Sep 14, 2026Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing 54 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BApartment$10,800—26016-90000-24845
Sep 14, 2026Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roofing Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BApartment$17,000—26016-20000-24800
Sep 2, 2026Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over new solid sheathing 33 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BDwelling - Single Family$9,900—26016-90000-23564
Aug 24, 2026Bldg-Alter/Repair: Application of an approved coating to an existing roofApartment$17,783—26016-10000-22531
Aug 11, 2026Bldg-Alter/Repair: Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over existing solid sheathing_29_Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Productlabeled and certified by Cool Roof Rating Council . Cool Roof may be required fornon-residential buildings per Title 24, Part 6, Section 149Apartment$13,000—26016-70000-21137
Aug 11, 2026Bldg-Alter/Repair: Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over existing solid sheathing_29_Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Productlabeled and certified by Cool Roof Rating Council . Cool Roof may be required fornon-residential buildings per Title 24, Part 6, Section 149Apartment$13,000—26016-70000-21134
Aug 5, 2026Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing __19__Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2B. INCLUDES DETACHED GARAGEDwelling - Single Family$15,000—26016-10000-19351
Jun 9, 2026Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing 15 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BDwelling - Single Family$3,000—26016-90000-15166
Jun 9, 2026Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over new solid sheathing 18 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BDwelling - Single Family$5,400—26016-90000-15165
Mar 12, 2026Bldg-Alter/Repair: Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over EXISTING solid sheathing __29_Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 149Apartment$14,500—26016-40000-06421
Mar 12, 2026Bldg-Alter/Repair: Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over EXISTING solid sheathing __10__Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 149Apartment$5,000—26016-40000-06411
Mar 9, 2026Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing 32 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BDwelling - Single Family$6,400—26016-90000-06360
Feb 17, 2026Bldg-Alter/Repair: Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over existing solid sheathing_135_Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone .For residential roof replacement>50% of the total roof area, apply Cool Roof Product labeled and certified byCool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part6, Section 141 2BApartment$114,700—26016-10000-04296
Feb 10, 2026Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over new solid sheathing 20 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BApartment$6,000—26016-90000-03832
Dec 29, 2025Bldg-Alter/Repair: Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over existing solid sheathing_29_Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone .For residential roof replacement>50% of the total roof area, apply Cool Roof Product labeled and certified byCool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part6, Section 141 2BDwelling - Single Family$10,000—25016-10000-37454
Aug 12, 2025Bldg-Alter/Repair: Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over existing solid sheathing _45_Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement>50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141 2BMiscellaneous Bldg/Structure$34,500—25016-10000-24479
Jun 11, 2025Bldg-Alter/Repair: Eplan:Supplemental to permit # 22010-10000-04258 to revise plans : Change the height of building & change the type of construction from type II-B to type II-A & change the layout of upper roof deck & minor floor layout changesOffice$280,000—22010-10002-04258
May 29, 2025Bldg-Alter/Repair: Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over new solid sheathing___35___Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141 2BMiscellaneous Bldg/Structure$20,000—25016-10000-17521
May 22, 2025Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over new solid sheathing 5 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BGarage - Private$1,500—25016-90000-16869
Mar 13, 2025Bldg-Alter/Repair: Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over existing solid sheathing _10_Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement>50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part6, Section 141 2BDwelling - Single Family$10,300—25016-30000-07053
Jan 23, 2025Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over new solid sheathing 32 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BMiscellaneous Bldg/Structure$9,600—25016-90000-02068
Jan 22, 2025Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing 40 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BDwelling - Single Family$8,000—25016-90000-01843
Nov 21, 2024Bldg-Alter/Repair: Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over existing solid sheathing 17 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BOffice$5,500—24016-10000-37219
Nov 18, 2024Bldg-Alter/Repair: Application of an approved coating to an existing roofCondo-Multi Family$30,000—24016-20000-36865
Nov 7, 2024Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing 7 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BOffice$1,400—24016-90000-35719
Nov 7, 2024Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing 26 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BOffice$5,200—24016-90000-35718
Nov 7, 2024Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over new solid sheathing 23 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BApartment$6,900—24016-90000-35717
Nov 4, 2024Bldg-Alter/Repair: Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone . For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roofing Rating Council . Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0 2BOffice$26,000—24016-20000-34961

Plumbing: 13 permits

From Jan 30, 2020 to Nov 22, 2023. Fewer than 5 plumbing permits since October 3, 2024 carry a declared value, so no range is computed; the rows are below.

Since October 3, 2024, 0 listed below. Earlier permits, 13, are on their house pages: 2023: 4 · 2021: 4 · 2020: 5.

IssuedWorkBuildingDeclared valueContractor as filedPermit

Heating and cooling: 7 permits

From Aug 19, 2020 to Dec 2, 2024. Fewer than 5 heating and cooling permits since October 3, 2024 carry a declared value, so no range is computed; the rows are below.

Since October 3, 2024, 1 listed below. Earlier permits, 6, are on their house pages: 2024: 2 · 2022: 1 · 2021: 1 · 2020: 2.

IssuedWorkBuildingDeclared valueContractor as filedPermit
Dec 2, 2024Bldg-Alter/Repair: 28 window . Window and door change-out (same size & type) for residential buildings. Dual glazing, labeled and certified by National Fenestration Rating Council , is required for doors and windows replaced in all residential buildings, three stories or less, per Title 24, Part 6, Section 150.2 1B.2 bathroom .Bathroom remodel for residential buildings .Kitchen remodel for residential buildingsDwelling - Single Family$45,000—24016-90000-38077

Electrical: 1 permit

From Aug 4, 2023 to Aug 4, 2023. Fewer than 5 electrical permits since October 3, 2024 carry a declared value, so no range is computed; the rows are below.

Since October 3, 2024, 0 listed below. Earlier permits, 1, are on their house pages: 2023: 1.

IssuedWorkBuildingDeclared valueContractor as filedPermit

Solar: 1 permit

From Jun 8, 2022 to Jun 8, 2022. Fewer than 5 solar permits since October 3, 2024 carry a declared value, so no range is computed; the rows are below.

Since October 3, 2024, 0 listed below. Earlier permits, 1, are on their house pages: 2022: 1.

IssuedWorkBuildingDeclared valueContractor as filedPermit

Addresses on this street with a page

Source